PARGDR Generate Draft Revenue Is Generating Revenue Amount Higher than Anticipated (Doc ID 2786526.1)

Last updated on JUNE 25, 2021

Applies to:

Oracle Project Billing - Version 12.2.9 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.9 version, Revenue

ACTUAL BEHAVIOR
---------------
Project is using same Burden schedule for Cost and Revenue.

But Cost and Revenue is different. Revenue is getting amount say 1234.12 is getting added to the revenue.
 

EXPECTED BEHAVIOR
-----------------------
Cost and Revenue should be same

 

STEPS
--------

1. Navigate to Projects form.
2. Select option Burden Multipliers> Cost Burden Schedule. Pick a Cost Burden schedule.
3. Select option Bill rates> Standard Billing Schedules. Pick the Burden schedule, and pick same Schedule as Cost Burden Schedule for Labor or Non-labor.
    With this setup Cost and Revenue amounts should be same
4. Enter Expenditures from pre approved batch entry form. Run PRC: Distribute Labor Costs and run PRC: Generate Draft Revenue For Single Project.
5. Revenue amount is higher, few expenditure amounts from previous runs are always getting added to the revenue total.

 

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.