Resource Usage Variance (RUV) Calculated by OPM Pre-Processor, Even Though Resource Usage in Batch Matches Usage in Costing Recipe
(Doc ID 2793185.1)
Last updated on APRIL 04, 2023
Applies to:
Oracle Process Manufacturing Financials - Version 12.2.8 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.8 version, Subledger Accounting
ACTUAL BEHAVIOR
---------------
OPM PreProcessor (OPP) is calculating RUV variances for a batch, but all of the resource usages seem to be equal to those in the costing recipe.
This seems to happening specifically for resources set to Fixed scaling.
EXPECTED BEHAVIOR
-----------------------
Expect there to be no RUV when the batch actual usage matches the costing recipe usage.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run OPP (OPM Financials > OPM Accounting Pre-Processor).
2. Run the Detailed Subledger Report (View > Requests > Submit New Request) and see the variance, or look at the data in GMF_XLA_EXTRACT_HEADERS/LINES tables using sql.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |