Error PA_NO_BUDGET_YEAR_DEFINED While Baselining Project Budget
(Doc ID 2826969.1)
Last updated on DECEMBER 09, 2021
Applies to:
Oracle Project Costing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.9 version, Funds Check
When attempting to baseline budget,
the following error occurs.
ERROR
-----------------------
PAPA_NO_BUDGET_YEAR_DEFINED
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Go to Project responsibility.
2. Open Budget form.
3. Query project number and budget type.
4. Click on Baseline button.
Changes
Cause