Planned Cost for the Resource Assignment Not Changing After Changing the Rate in Rate Schedule And Refresh Cost Rates Is Executed, Why (Doc ID 2834346.1)

Last updated on JANUARY 18, 2022

Applies to:

Oracle Project Planning and Control - Version 12.1.1 and later
Information in this document applies to any platform.

Goal

Planned Cost for the Resource assignment not changing after changing the Rate in Rate schedule and Refresh cost rates is executed, why

Steps:

1.Go into the  Project Super User Responsibility  

2.Navigate to workplan -> current working version -> Update task ->Resource -> assign the Resource and enter the planned quantity .

3.Navigate to Project Costing Responsibility -> Expenditure -> pre approved batch -> Enter the actual quantity same as planned quantity .

4. Run the Below Concurrent Process .

a.PRC:distribute process

b.PRC:Update project and Resource Base Summaries

c.PRC:Update Project Performance Data 

4.Navigate to Expenditure -> Rate Schedule ->select the Rate Schedule -> Change the Rate Schedule for the employee .

5.Navigate to workplan -> current working version -> Update task ->select Resource ->select Refresh cost rates .

 


 

Solution

To view full details, sign in with your My Oracle Support account.