Seconds are added when Rescheduling Production Order longer than a day
(Doc ID 2849617.1)
Last updated on AUGUST 16, 2024
Applies to:
Oracle Process Manufacturing Process Execution - Version 12.2.10 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.10 version, Other Issues
ACTUAL BEHAVIOR
---------------
After applying patches 33276049:R12.GME.C and 32764545:R12.GMP.C seconds are added when rescheduling longer than 1 day
Problem
-------------
Tried to reschedule Production Order which is longer than a day – the example order lasts exactly 6 days and 10 hrs.
There are 6 seconds was added.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open Gantt Chart -> Choose Production Order -> Reschedule Production Order:
2 Start Date and schedule out Production Order which is longer than a day
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |