Publish Workplan Error ‘Task Number Already Exists’ Even Though Task Number Is Unique
(Doc ID 2857149.1)
Last updated on DECEMBER 10, 2024
Applies to:
Oracle Project Planning and Control - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
When trying to publish the workplan getting the below error, even though task number is unique
Error
Task Number Already Exists’
Steps:
1. Go into the Project Super User responsibility
2. Navigate to Project:Delivery-> OPen the project
3. Navigate to Workplan-> Working Version -> Publish the workplan
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |