Symptoms

When PRC: Interface Supplier Costs (PAAPIMP) is run for Purchase Order (PO) Receipts, those receipts are interfaced to projects without running "Create Accounting - Receiving" in Final mode.

Steps to reproduce:

  1. From a Purchasing responsibility, navigate to: Purchase Orders > Purchase Orders.
  2. Create PO distribution with accrue at receipt = 'Y'.
  3. Save and approve PO.
  4. Navigate: Receiving > Receipts.
  5. Receive PO and save.
  6. Navigate: Receiving > Receiving transactions.
  7. Receive PO and save.
  8. Without running "Create Accounting - Receiving", switch to Projects responsibility.
  9. Run: "PRC: Interface Supplier Costs" process with "Interface Receipt Accruals" = 'Yes'.
  10. The PO receipt got interfaced in projects.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.