Multiple Error Messages When Job Order Status Changed From Complete To Complete-no Charges
(Doc ID 2871714.1)
Last updated on NOVEMBER 21, 2022
Applies to:
Oracle Work in Process - Version 12.2.9 and laterInformation in this document applies to any platform.
Symptoms
When attempting to update job to complete no charges status, the following error occurs:
PO/requisition was not automatically canceled.
Cause: PO/requisition cannot be canceled if:
1. PO/requisition was in a status other than Approved, or Rejected.
2. PO/requisition was already closed, or finally closed, or canceled, or put on hold.
Error:
&MESSAGE (MESSAGE=)
Error:
Document #138669-148, Line #24,Shipment #1 :
Shipment is Fully Received. Quantity Received is [14] and Quantity Ordered is [14].
Error:
Document #138669-148:
Cancel action at LINE_LOCATION Level is invalid for this document.
(ACTION=CANCEL)
Error:
&MESSAGE (MESSAGE=)
--- LOG --
Cause: PO/requisition cannot be canceled if:
1. PO/requisition was in a status other than Approved, or Rejected.
2. PO/requisition was already closed, or finally closed, or canceled, or put on hold.
Error:
&MESSAGE (MESSAGE=)
Error:
Document #138669-148, Line #24,Shipment #1 :
Shipment is Fully Received. Quantity Received is [14] and Quantity Ordered is [14].
Error:
Document #138669-148:
Cancel action at LINE_LOCATION Level is invalid for this document.
(ACTION=CANCEL)
Error:
&MESSAGE (MESSAGE=)
--- LOG --
FND log shows
wip.plsql.wip_osp.cancelPOReq return status: U
The issue can be reproduced at will with the following steps:
1. Manufacturing and Distribution Manager responsibility
2. WIP -> Discrete -> Discrete Jobs navigation
3. search for work order and change its status
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |