Symptoms

When attempting to update job to complete no charges status, the following error occurs:

PO/requisition was not automatically canceled.

Cause: PO/requisition cannot be canceled if:
1. PO/requisition was in a status other than Approved, or Rejected.
2. PO/requisition was already closed, or finally closed, or canceled, or put on hold.

Error:
&MESSAGE (MESSAGE=)

Error:
Document #138669-148, Line #24,Shipment #1 :
Shipment is Fully Received. Quantity Received is [14] and Quantity Ordered is [14].

Error:
Document #138669-148:
Cancel action at LINE_LOCATION Level is invalid for this document.
(ACTION=CANCEL)

Error:
&MESSAGE (MESSAGE=)

--- LOG --

 

FND log shows

wip.plsql.wip_osp.cancelPOReq return status: U


The issue can be reproduced at will with the following steps:
1. Manufacturing and Distribution Manager responsibility
2. WIP -> Discrete -> Discrete Jobs navigation
3. search for work order and change its status

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.