My Oracle Support Banner

Copy Item Costs Across Organizations summarize all sub-element into one Element for example Material (Doc ID 2873768.1)

Last updated on APRIL 04, 2025

Applies to:

Oracle Cost Management - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

 ACTUAL BEHAVIOR  
---------------

Copy item cost from manufacturing org to Trading organization Required:-

When we are copy item cost from Org (Manufacturing organization)
To Trading Organization

Resource and overhead cost should be sum in item material cost


Example.

Mfg org item Unit cost for item XXXX
Unit Cost 74.44349 = Material 70.64560 Resource 0.80450 Overhead 2.99339

Trading org Item unit cost
Unit Cost 74.44349= Material Cost 74.44349 Resource Cost 0 Overhead cost 0


EXPECTED BEHAVIOR
-----------------------
Resource and overhead cost should be sum in item material cost Example.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. When we are copy item cost from Org (Manufacturing organization) To Trading Organization

Resource and overhead cost should be sum in item material cost
Example.

2. Mfg org item Unit cost for item 71000330
Unit Cost 74.44349 Material 70.64560 Resource 0.80450 Overhead 2.99339

3. Trading org Item unit cost
Unit Cost 74.44349 Material Cost 74.44349 Resource Cost 0 Overhead cost 0

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.