Unable To Update Task Schedule Dates on the Self Service Web Application as the Following Error is Received: "Row 1 Error - Project: 'XXX' Invalid organization. You cannot use the specified organization to create projects of this project type class.." (Doc ID 2897965.1)

Last updated on SEPTEMBER 28, 2022

Applies to:

Oracle Project Foundation - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

When altering the task end date in the self service application after setting the Organization Classifications: "Project Task Owning Organization" | "Others" |  "Project Type Class Information" as below, error is returned.

Allow Entry of Indirect Projects = No
Allow Entry of Capital Projects = No
Allow Entry of Contract Projects = No

When making this exact same change in the forms based application, the error is not returned. Users are not allowed to save the change in the self service application.  

 

ERROR:

Row 1 Error - Project: 'XX' Invalid organization. You cannot use the specified organization to create projects of this project type class. Choose a different organization or add the project type class to the current organization. (TASK=X)

The message is PA_INVALID_PT_CLASS_ORG_AMG


STEPS TO REPRODUCE:

1. The setup for an organization is (example):

Projects responsibility | Setup | Resources and Organization | HR Foundation | Work Structures | Organization

Organization form:  Name = Organization 1
Organization Classifications: "Project Task Owning Organization" => Click "Others".
In the "Project Type Class Information" screen, set:
Allow Entry of Indirect Projects = No
Allow Entry of Capital Projects = No
Allow Entry of Contract Projects = No

2. Steps to update schedule dates:

Project Super User 
a. Open Project Number = Project 1, Organization = Organization 1
b. From Shortcuts LOV menu, choose "Update Tasks"
c. Now in Workplan | Tasks | Update Tasks screen:  Expand all tasks | click update pencil next to task 2.0 (Task Name = 2) to update
d. Click on the "Schedule" tab:

Current Schedule:
              Start Date        Finish Date
Schedule 01-Jan-2015     01-Jan-2015

Change Finish Date, i.e. 01-Jan-2016 | click save
 
3. Error Received: Row 1 Error - Project: 'Project 1' Invalid organization. You cannot use the specified organization to create projects of this project type class.  Choose a different organization or add the project type class to the current organization. (TASK=2)

Changes

 Altered a task's end date. 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.