My Oracle Support Banner

Why does the Supply/Demand Form Show a Date for a Component in a WIP Job that is Different from the Dates on the Job Header? (Doc ID 2898025.1)

Last updated on SEPTEMBER 28, 2022

Applies to:

Oracle Work in Process - Version 12.2.5 and later
Information in this document applies to any platform.

Goal

The Supply/Demand Form (Inventory > On-hand, Availability > Item Supply/Demand) shows a demand date of September 1 for a  component for some work orders even though the dates on the job header are different. For example, on one of the jobs the Start Date and Completion Date on the job header are far in the future, and the Released Date on the job header is August 17. Why does the Supply/Demand screen show September 1?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.