My Oracle Support Banner

PAIGEN: PRC: Generate Intercompany Invoices for a Single Project Errors With, There is No Schedule Line Found for the Schedule Id, Provider, Receiver Organization and Operating Unit Combinations Using Transfer Price Rules (Doc ID 2916686.1)

Last updated on JULY 16, 2024

Applies to:

Oracle Project Billing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Concurrent process PRC: Generate Intercompany Invoices for a Single Project program not processing the transaction , showing the below error
the following error occurs.

ERROR
-----------------------
There is no schedule line found for the schedule id, provider, receiver organization and operating unit combinations using transfer price rules

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1.Go into the project responsibility
2.Navigate to View-> Request

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.