My Oracle Support Banner

PAXPREPR: Unable To Update Budgetary Control For New Project (Doc ID 2917365.1)

Last updated on DECEMBER 22, 2022

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
User created a new project and would like to change control level of budgetary control to None from Absolute.

However user is not able to modify control level of project.

EXPECTED BEHAVIOR
-----------------------
User should be able to change control level of budgetary control for new project

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to Project responsibility
2. Open Project form
3. Query existing project and click on Copy button.
4. Create a new project
5. Navigate to Options > Budgetary Control Level
6. Try to modify budgetary control level at specific level


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution