Symptoms

The 'PA' and 'GL Periods for PA' are closed for January on February 6th  However, on February 8th, a new Web ADI accrual transaction is entered and posted into January. How is this possible when January is already closed? 

Relevant facts:

1.  The profile option PA: Enable Enhanced Period Processing is set to YES (Enabled)
2.  The expenditure item date on the transaction is 31-JAN

Steps to Reproduce:

1.  Enter in an accrual expenditure item in WebADI with the Accrual Flag = Y (Project Super User | Projects: Spreadsheets | Choose the appropriate sheet).
2.  Run the PRC:  Transaction Import (Project Costing Super User | Other | Requests | Run) and bring the item into Projects.
3.  Query the expenditure item up in the Expenditure Inquiry (Project Costing Super User | Expenditure | Expenditure Inquiry | Project | Query the Trans Id | Cost Distribution Lines) and note the PA and General Ledger (GL) periods are both January and not February.

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution