New Employees Do Not Appear In PJRM After Running PRC:Maintain Project Resources (Doc ID 295561.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Resource Management - Version 11.5.9 to 11.5.10.2 [Release 11.5 to 11.5.10]
Information in this document applies to any platform.

Symptoms

Added new periods to the Application calendars (GL, PA, PRJM) and ran the generate calendar process for Project Resource Management with success.    Subsequently ran the Maintain Project  Resources for some new resources (employees) added in HR but they do not appear in PJRM or in PA_RESOURCES.

 

Cause

Sign In with your My Oracle Support account