Overheads Based On Resources Are Not Being Considered By PAC (Doc ID 296268.1)

Last updated on OCTOBER 29, 2016

Applies to:

Oracle Cost Management - Version 11.5.9 to 11.5.10.3 [Release 11.5]
Information in this document applies to any platform.

Symptoms

You have overheads that must be charged during move transactions for discrete jobs. All the overheads are based on resource units. Rates for these resources are not entered since you don't charge resources to the cost of the items. Only 'Item' basis overheads are considered by Periodic Average Costing (PAC), while resources with their basis set to 'Resource Units' are ignored. In the perpetual costing method (Standard), both 'Item' and 'Resource Units' are considered.

Cause

Sign In with your My Oracle Support account