PAXCARVW: CIP Amount Showing As Expensed in Capital Projects Form for a Project. (Doc ID 3075334.1)

Last updated on MARCH 11, 2025

Applies to:

Oracle Project Costing - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

In the Capital project form Expensed field is populated instead of CIP amount.

The issue can be reproduced at will with the following steps:
1. Navigate to Projects responsibility.
2. Capitalization-> Capital Projects.
3. Check the CIP and expensed amount fields.

Cause