Unexpected Behavior Using Increment Date Parameter Each Run (Doc ID 339849.1)

Last updated on JUNE 24, 2016

Applies to:

Oracle Application Object Library - Version 11.5.0 to 11.5.10.0 [Release 11.5]
Oracle Concurrent Processing - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.
FORM:FNDRSRUN.FMB - Run Reports
FORM:FNDRSSET.FMB - Administer Report Sets
FORM:FNDCPMCP.FMB - Define Concurrent Program

Checked for relevance on 30-AUG-2012
Applications Install 11.5.7 to 11.5.10



Symptoms

A Concurrent Request or Request Set can be scheduled to run at specific intervals. If it is scheduled to run Periodically or On Specific Days there is the option to Increment Date parameters each run which will re-evaluate the value of each parameters of the following default type :

The functionality does NOT work for the other default types :

For these last default types the value obtained during the initial run of the concurrent program will be used for each subsequent scheduled request.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms