R11:PA:How do the Project and Task Dates in the Projects HTML Interface Tie to the Dates in the Form-Based Projects Application? (Doc ID 361507.1)

Last updated on SEPTEMBER 19, 2023

Applies to:

Oracle Project Planning and Control - Version 11.5.10.2 and later
Oracle Project Foundation - Version 11.5.10.2 and later
Information in this document applies to any platform.

Purpose

When viewing project start date and project finish date through either the Project Lists page or the Search Project page, the dates do not appear to tieback to the dates in the form based Projects application.   For example, in the form based application, the project start date might be 01-JAN-10 through project end date 31-DEC-10, but when you query up this same project in the Project List page in the HTML user interface, the dates for Project Start Date and Project Finish Date show as 01-JAN-10 through 01-JAN-10.

This document will attempt to explain these inconsistencies and describe in detail the various dates associated to projects and tasks and their functions.

Troubleshooting Steps

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Troubleshooting Steps
 How do the Dates in the Self-Service Web Application Tie to the Dates in the Form-Based Projects Application?
 What About the Project Start and Project Finish Date I see in the HTML pages?
 What are the Different Dates and How are they Populated?
 1. Target Dates:
 2. Scheduled Dates:
 3. Baseline Dates:
 4. Estimated Dates:
 5. Actual Dates:
 6. Transaction Dates:
 Date Columns
 Date Source and Function Matrix
 Upgrade
 Copy Project
 Quick Entry
 Display Order of Precedence for the Project Start and Project Finish Dates
 Quick Entry Date Adjusting Logic
 Structures
 Summary