Budget Type does not Upgrade to Plan Type

(Doc ID 387078.1)

Last updated on FEBRUARY 15, 2018

Applies to:

Oracle Project Planning and Control - Version 11.5.10.0 to 12.1.3 [Release 11.5.10 to 12.1]
Information in this document applies to any platform.

Symptoms

Ran "UPG: Upgrade Budget Types and Budget Versions” and it didn't upgrade all budget types.

Does upgrade program only upgrade the budget if there is a record in pa_budget_versions table where budget_type_code is not null?


Cause