Task Progress Update Is Allowed If The Predecessor Task Is Not Complete (Doc ID 395424.1)

Last updated on JUNE 14, 2017

Applies to:

Oracle Project Planning and Control - Version 11.5.10.2 to 12.2.3 [Release 11.5.10 to 12.2]
Information in this document applies to any platform.
Checked for relevance on 07-OCT-2015


Symptoms

When using a Finish-to-Start dependency for 2 tasks which are not subtasks of each other, the user is able to enter progress for the second task before the predecessor task is completed.

Task dependency is ignored when entering progress for a task when the predecessor task is not completed.


Cause