Move And Scrap Transactions Done Simultaneously Through WIP_MOVE_TXN_INTERFACE In The OSP Operation Errors Out And Does Not Create A Purchase Requisition (Doc ID 405535.1)

Last updated on OCTOBER 28, 2016

Applies to:

Oracle Work in Process - Version 11.5.10.2 to 11.5.10.2 [Release 11.5]
Information in this document applies to any platform.

Symptoms

When attempting to do Move Transactions and Scrap Transactions simultaneously through the interface table WIP_MOVE_TXN_INTERFACE the following error occurs:

ERROR
Requisition is in a pending status and cannot be updated or canceled.

Cause: Requisition is still in an interface table.

STEPS
The issue can be reproduced at will with the following steps:
1. Create a job.
2. Insert the move and scrap transactions more than once into the wip move interface.
3. Perform the to move action through interface.
4. The transactions error out.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms