ATP Does Not Honor Shipping Calendar - Schedule Ship Date Does Not Save On Work Day Saturday

(Doc ID 456786.1)

Last updated on SEPTEMBER 20, 2017

Applies to:

Oracle Order Management - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

A calendar was created, built, and assigned to an organization with the usage of Shipping. The calendar is set up for 6 days on, 1 day off; workdays are Monday through Saturday, inclusive. When entering a sales order in this organization and attempting to enter a scheduled ship date of a Saturday (e.g., 9/1/07) and saving, the scheduled ship date automatically reverts to the previous Friday (e.g., 8/31/07).

The problem seems to be that the scheduled ship dates are not referencing the shipping calendar but rather the production calendar, which is 5 days on, 2 days off.

Steps to Reproduce:
Created same calendar in a test instance and tried with several organizations -- same result.

Order Management Manager -> Shipping -> Setup -> Calendars -> Enter / Assign

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms