Symptoms

 

In a discrete job, when attempting to modify resource Scheduled Field from NO to YES and SAVE, the following error occurs:

APP-BOM-20861: Resource is not time-based. You cannot schedule a resource that is not time-based.

The issue can be reproduced at will with the following steps:

1.) Inventory-> Unit of Measure Classes  Created Unit of Measure Classes with Russian symbol ч
2) Inventory->Unit of Measure  Created Unit of Measure with Russian symbol ч
3) EAM-> Set Up-> Routing -> Resources  Created RESOURCE with UOM Russian symbol ч
4) This RESOURCE include to operation from Maintenance ROUTING (Activity)
5) Created Work Order
6) Work Orders -> Resources -> Scheduling: tried to modify Scheduled Field from NO to YES and SAVE and received ERROR (APP-BOM-20861)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms