ATP Does Not Provide Results Based On Subinventory Level Lead Times (Doc ID 469121.1)

Last updated on JULY 02, 2019

Applies to:

Oracle Order Management - Version 11.5.10.2 to 11.5.10.2 [Release 11.5.10]
Information in this document applies to any platform.

Goal

Will ATP use the Sub-Inventory level Lead Time setups for scheduling order lines and displaying the availability?


STEPS
_______

1. Order Management Super User
2. Scheduling > Run ATP Data Collections
3. Item X in FGI = 2 available
    Item X in Refurbish = 2 available
4. Orders, Returns > Sales Orders
5. Enter sales order (Item = X, Qty = 3, Subinventory = Refurbish)

Returned scheduling results through ATP are:
4 available on request date - OK to ship 3 from refurbish.

Expected the results to be returned to show only 2 were available in Refurbish, thus scheduling would occur at the infinite supply date assigned in the ATP rule that is assigned to Item X.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.