Symptoms

The Task Percent Complete is not getting updated using AMG API.  If you set the  As_Of_Date Parameter to Before Sysdate or Sysdate, you cannot update the Task Percent Complete by API.

The following is received:  API error:
The As of Date is invalid. Please check the Progress Cycle of the project.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References

This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.