Setting the AS_OF_DATE Parameter to Before Sysdate or Sysdate Receive Error "The As of Date is Invalid" (Doc ID 552743.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 11.5.10.0 and later
Information in this document applies to any platform.

Symptoms

The Task Percent Complete is not getting updated using AMG API.  If you set the  As_Of_Date Parameter to Before Sysdate or Sysdate, you cannot update the Task Percent Complete by API.

The following is received:  API error:
The As of Date is invalid. Please check the Progress Cycle of the project.

Cause