My Oracle Support Banner

PAC - When Total Operations is Negative, the Value in WIP Operation is not Relieved (Doc ID 553836.1)

Last updated on APRIL 04, 2025

Applies to:

Oracle Cost Management - Version 11.5.10.2 to 11.5.10.3 [Release 11.5]
Information in this document applies to any platform.
PAC - Periodic Average Costing
CSTPWASB.pls

Symptoms

PROBLEM STATEMENT:
-----------------------------


In Oracle Cost Management, in Periodic Average Costing (PAC) if the total
operations cost is negative, then the value in the operation may not be relieved
even if the total assembly's cost is positive.


EXPECTED BEHAVIOR
-----------------------------------
Assembly Completion's cost should be correct even when the component requirement is negative.



-- Steps To Reproduce:
The issue can be reproduced at will with the following steps:
1. Responsibility: Work in Process
2. Navigation Path: Discrete Jobs (Assembly Pull).
3. Create the job.
4. Perform component issue of the regular component.
5. Move and complete.
6. Verified the negative component is issued.

1. Responsibility: Cost Management
2. Navigation Path: Periodic Costing
3. Run PAC processes.
4. Check the accounting entry for Assembly Completion.


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.