Cstppccb.Pm_process_txn_mmt (185) Failed To Get Expenditure Type (Doc ID 555429.1)

Last updated on JANUARY 13, 2017

Applies to:

Oracle Cost Management - Version 12.0.3 and later
Information in this document applies to any platform.
***Checked for relevance on 09-JUL-2013***


Symptoms

-- Problem Statement:
On 12.0.3 in Production:
When Issued material from Inventory to project and ran Project Cost Transfer/Cost Collection
Manager . The cost is not getting transferred to Project as it is giving the following error:

ERROR
---------

CSTPPCCB.PM_PROCESS_TXN_MMT (185) FAILED TO GET EXPENDITURE TYPE



-- Steps To Reproduce:
The issue can be reproduced at will with the following steps:
1.Create & Transact Move Order
2.check that the item is costed .
3. Run Project Cost Transfer/Cost Collection Manager .
4. Check material Transaction , Reason ,Reference Tab. Getting the error here in the Transferred
to Project Column.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms