Symptoms

When a manually created Work Order is completed, the next service date is not automatically generated.
The Forecast must to be run so that the Next Service Date is modified.

You expect system to update the Next Service Date when the manually created Work Order is completed.

The issue can be reproduced at will with the following steps:
1. Maintenance Super User Responsibility (EAM Self Service)
2. Nav: Assets - Rebuildable Subinventory
3. Query an Item. Note the Next Service Date.
4. Manually create a Work Order for the Item.
5. Complete the Work Order.
6. Query the Item again in eAM Self Service - Assets - Rebuildable Inventory
7. Notice Last Service Start/End Dates are updated. However, the Next Service Start Date is not updated.
The Next Service End Date is Null.
8. Run a Forecast for the Item.
9. Notice the Next Service Start Date gets updated with the correct date.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms