R11 Resource Breakdown Structure Version Not Updated In Templates Or Projects (Doc ID 604114.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 11.5.10.0 to 11.5.10.2 [Release 11.5.10]
Information in this document applies to any platform.

Symptoms

New versions of our resource breakdown structure are not being updated to our templates or existing projects.

-- Navigation> Create new Resource breakdown structure version > run the PRC: Process Resource Breakdown Structure Updates and applicable projects do not get updated.

Example: 
Project XXXX, the current date is open starting from 15-MAY-2008.
The Resource Breakdown Structure "Exp Cat Type" has 7 versions.
7 is the working version
6 is the current reporting version
It is a Primary Reporting structure type and used in Workplan and Financial Plan.

Per documentation:
To update projects with the latest resource breakdown structure version, run the
PRC: Process Resource Breakdown Structure Updates process. This process affects
only projects that reference this resource breakdown structure. The process updates
the projects to use the frozen version, which has a system date between the start and
end dates of the resource breakdown structure version.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms