How Do You Change A Check Date That Falls on a Holiday in the Following Year? (Doc ID 746391.1)

Last updated on JUNE 14, 2017

Applies to:

Oracle Payroll - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

While reviewing check dates for a payroll, it is found that a check falls on a holiday.  How can the check date be changed to fall on a work day?

 

Example:

When looking at the payment periods for 2009, there should be 27.

Oracle has only 26 with the last payment date of the year falling on 18-DEC-2009 and the first pay date of 2010 falling on 01-JAN-2010.

01-JAN-2010 is a Federal Holiday and therefore will be paid on 31-DEC-2009, which should make 27 pay periods for 2009.

How do we correct this?

 



Solution