When Work Order Is Closed, Work Request Status Still On Work Order (Doc ID 763745.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Enterprise Asset Management - Version 11.5.10.2 to 12.1.3 [Release 11.5 to 12.1]
Information in this document applies to any platform.
***Checked for relevance on 17-Feb-2014***


Goal

When Work Order is closed, Work Request status still On Work Order.

Steps to Reproduce:
1. Create a work request.
2. Approve the work request.
3. Create a work order from the work request.
4. Closed the work order.
5. Status on the work request remains "On Work Order"

Solution