Symptoms

Project revenue posted to the current period, FEB-09, versus DEC-08 even though both periods were open.  The expectation was that the revenue would post to the earliest open period. Why did this happen?

1.  The PA:  Enable Enhanced Period Processing profile option was set to NO at the SITE level

2.  The 'Maintain Common PA and GL Periods' Implementation Option was NOT checked


.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms