R12: Actual Cost Not Update In Workplan (Doc ID 806774.1)

Last updated on OCTOBER 24, 2016

Applies to:

Oracle Project Planning and Control - Version 12.0.4 to 12.0.4 [Release 12.0]
Information in this document applies to any platform.

Symptoms

Actual cost is not updated in workplan

Steps To Reproduce:
1. Create transaction for a project.
2. Update the project summary amounts and view project costs successfully in PSI.
3. Run request 'PRC: Update Project and Resource Base Summaries' and 'PRC: Update Project Performance Data'.
4. Query the WBS.
5. Actual cost is not updated.

Cause