R11i: R12: PA: Currency Conversion Failed For Task Id Message Code PA_NO_PROJFUNC_CURR_RATE. (Doc ID 822612.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 11.5.10.0 and later
Information in this document applies to any platform.

Symptoms

We receive an exception during the PRC: Refresh Project Performance Data process.
The exception states:

The following projects may have incorrect actual amounts on Workplan pages. For accurate actual
amounts, please correct the exceptions and resubmit the PRC: Update Project Performance Data
process.

Project Number Exception Reason
===================== =================
S-BAXX-03-00-000 Currency conversion failed for Task Id: 151647, Res Id: 1024 Message
code: PA_NO_PROJFUNC_CURR_RATE From currency: USD To currency: GBP

And the log file states:
: GET_SUMM_ACT: Project Id: 51336 As of Date: 21-APR-09 Project Level: 1
: GET_SUMM_ACT: Currency conversion failed for Task Id: 151647, Res Id: 1024 Message code:
PA_NO_PROJFUNC_CURR_RATE From currency: USD To currency: GBP

Also:
We do not use a Corporate Rate as standard, only user rates are defined when invoices are
converted to project functional currency.
And, a resource list change was made prior to this issue.

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms