Load Config Results Incorrect
(Doc ID 837738.1)
Last updated on JULY 20, 2024
Applies to:
Oracle Transportation Operational Planning - Version 5.5.05.03 and laterInformation in this document applies to any platform.
This problem can occur on any platform.
Symptoms
Two orders are planned onto a shipment. Both orders have 100 items each. The expected result is
one shipment with one equipment and both orders fit the equipment. This worked well, but changed
after RU3 was applied. The planning result now is:
100 items of the first order, and 74 items of the second order go on one equipment. The remaining
26 items of the second order go on a second shipment. All items of the second order are only
stacked two high, despite they can be stacked three high (and were before the RU3 was installed).
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|