Changing the Required_quantity in Material Requiremets form (WIPMRMDF.fmb) does not change automatically the Quantity_Per_Assembly in Release 12. WHY? (Doc ID 858907.1)

Last updated on MARCH 04, 2017

Applies to:

Oracle Work in Process - Version 12.0.0 and later
Information in this document applies to any platform.

Goal

When changing the "required quantity" field for a discrete job, the quantity "per assembly" field is not recalculated. Instead, the Yield field is recalculated.

In 11.5.10.2 and 11.5.9, the "per assembly" field was recalculated when the "required quantity field" was changed.

WIP => Job/Schedule Details => Material Requirements

WHY?

Solution