DEFAULT MATERIAL SUB-ELEMENT IS NOT SET FOR NEWLY CREATED ITEMS IN A STANDARD COSTING METHOD ORGANIZATION (Doc ID 870186.1)

Last updated on NOVEMBER 02, 2014

Applies to:

Oracle Cost Management - Version: 11.5.10.2 to 11.5.10.3 - Release: 11.5 to 11.5
Information in this document applies to any platform.
***Checked for relevance on 09-Oct-2011***

Symptoms

-- Problem Statement:
On 11.5.10.2 

Newly created items do not include the default cost Material sub-element for Standard Costing.

EXPECTED BEHAVIOR
-----------------------------------
Expect items to include default cost material sub-element on a standard costing organization.

-- Steps To Reproduce:
The issue can be reproduced at will with the following steps:
1) normal method is to use Item interface to create new Master Item and Org  Items using item templates.
2) manually create new items in Oracle master Org with template, assign to Inventory Org and set Org attributes by applying Org level template. Check Item Costs and see there is no material sub-element -- only material overheads are defaulted.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms