Dunning Letter Generate Runs And Never Finishes

(Doc ID 878014.1)

Last updated on FEBRUARY 09, 2018

Applies to:

Oracle Receivables - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

Dunning Letter Generate never completes after 10g database upgrade.

Responsibility:  Receivables
Navigation:  Print Document > Dunning Letter > Single Request
Dunning Letter Generate (with the following parameters)
CUSTOMER
2017/08/13
CYCLE 1
CYCLE 1
(Arguments 5 through 10 are Blank)
DAYS_OVERDUE
N
(Arguments 13 through 17 are Blank)
N

This process creates finance charges for your bills, so it’s holding up the billing process.

Changes

 

Cause