Accessorial Time Not Getting Considered In Work Time of Rate Service. (Doc ID 882332.1)

Last updated on JULY 09, 2014

Applies to:

Oracle Transportation Management - Version: 5.5.05.05
This problem can occur on any platform.

Symptoms

-- Problem Statement:

OTM is not considering the added accessorial time when calculating and validating the shipment work time against the rate service Max Work Time. Thus, the shipment is built with work time greater than the max work time although the rate service configured with Shipment Infeasible When Time Exceeded.

-- Steps To Reproduce:
The issue can be reproduced at will with the following steps:

1- Configure a rush hour rate service (Rush Hour calendar) with accessorial time and Max Work Time Usage Type of Shipment Infeasible When Time Exceeded.
2- Plan a shipment and notice that work time is greater than the max work time.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms