Calculate Manufacturing Lead Times Fails With APP-WIP-25084: Operation Dates Fall Outside Defined Calendar Days (Doc ID 883482.1)

Last updated on OCTOBER 27, 2016

Applies to:

Oracle Work in Process - Version 11.5.10.2 to 11.5.10.2 [Release 11.5]
Information in this document applies to any platform.
***Checked for relevance on 06-DEC-2013***

Symptoms

Calculate Manufacturing Lead Times fails with an error of:
APP-WIP-25084: Operation dates fall outside defined calendar days
Cause: Oracle Work in Process is unable to schedule your job or schedule because operation dates fall outside defined calendar dates.
Action: You can define additional calendar dates in Oracle Bills of Material or decrease your job or schedule quantity.