Cost Collection Of Material TXN Err CSTPPCCB.pm_process_txn_mmt(170): CSTPPCCB.pm_insert_pti_pvt

(Doc ID 943690.1)

Last updated on APRIL 17, 2017

Applies to:

Oracle Project Manufacturing - Version 12.0.0 to 12.0.0 [Release 12]
Information in this document applies to any platform.

Symptoms

On 12.0.5 in Production:
Cost Collection of WIP Material issues fails with the following error message.

ERROR

Steps
The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process
2. Navigation: Discrete -> Discrete Job
3. Release Discrete Job for item hard pegged to Project and Task.
4. Issue Material to job via Component Pick Release (Form).
(PJM "Allow Cross Project Issues" enabled and all projects are in the same Planning Group.)
5. Transact Move Order from non Project locator.
6. Cost Manager costs transaction.
7. Run Cost Collection Manager request (0 days uncollected).
8. Error messages appear in Material Transaction table and no cost data is collected to the project

Changes

 

Cause

Sign In with your My Oracle Support account