Symptoms

ACTUAL BEHAVIOR
---------------
 Musharaka Partial settlement with reduce Tenor, Tenor Reduced but increased the EMI

EXPECTED BEHAVIOR
-----------------------
System should reduce the tenor but EMI should not be increases and any residual should be adjusted in bullet schedule.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
Musharaka finance contract is booked with CIDACCNT screen.
Prepayment initiated with Reduce tenor option using CIDPYMNT screen.
After prepayment system has reduced the tenor but increased the EMI amount as well.
before payment EMI was 4680, After prepay increased to 4943.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, EMI has been changed

Changes

The original EMI was built by considering the Moratorium amount. However during re-calculation, system was considering the original EMI as base and adding the Moratorium amount and derived the new EMI. This has resulted the change in EMI as well.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.