Does GOP Scheduling Split Sales Order Lines if Requested Quantity is Available in More than One Inventory ? (Doc ID 1590213.1)

Last updated on JANUARY 20, 2017

Applies to:

Oracle Fusion Distributed Order Orchestration - Version 11.1.5.0.0 to 11.1.9.2.0 [Release 1.0]
Oracle Fusion Order Management Cloud Service - Version 11.1.11.1.0 and later
Oracle Fusion Global Order Promising - Version 11.1.11.1.0 and later
Information in this document applies to any platform.
***KM Review - Dec 2016 - Checked for Relevance***

Goal

Does GOP scheduling split sales order lines if requested quantity is available in more than one Source ?

This requirement is best illustrated by an Example:

1. User Creates an Order for 3 of Inventory Item - XXX
2. Sourcing Rules have been defined where the item is to be first sourced from Org AAA, then Org BBB
3. Available qty in Org AAA is 1
4. Available qty in Org BBB is 10

In this scenario will the sales order line be split so that the available qty in Org AAA is scheduled and the remaining qty is sourced from Org BBB 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms