18046825:Resource Additions To PRBS Not Reflecting In Projects (Doc ID 1613351.1)

Last updated on JANUARY 27, 2015

Applies to:

Oracle Fusion Project Costing - Version 11.1.5.0.0 and later
Information in this document applies to any platform.

Goal

Any resource added to a PRBS (Planning and Reporting Resource Breakdown Structure) does not make the resource automatically available at the project level for assignment. We have to refresh the project by re adding the PRBS to the project.
 

Solution