PJF: Tasks Are Repeating On Manage Project Plan

(Doc ID 1622079.1)

Last updated on JUNE 23, 2018

Applies to:

Oracle Fusion Project Foundation - Version 11.1.6.0.0 to 11.1.8.0.0 [Release 1.0]
Information in this document applies to any platform.

Symptoms

On Manage Project Plan for a Project, same tasks are displayed multiple times.

Expected Behavior
Manage Project Plan tasks should not show tasks duplicated.

Replication Steps
1. Create Project from a template and baselined.
2. Changed the Project's organization from Basic Information
3. Changed task level organization for a few tasks.
4. Created a new resource for task 2.0 and increased the span of the task by changing start date.
5. Clicked on save.
6. Changed the task level organization of task 2; deleted existing resources for task 2, and added a new resource. Clicked on Save.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms