In Scope Of Plan Components Copy Formula Is Not Working As Expected : Rearnings are Wrong (Doc ID 1641603.1)

Last updated on NOVEMBER 05, 2016

Applies to:

Oracle Fusion Incentive Compensation Cloud Service - Version 11.1.7.0.0 and later
Oracle Fusion Incentive Compensation - Version 11.1.7.0.0 and later
Information in this document applies to any platform.

Symptoms

On :  11.1.7.0.0 version, Manage Incentive Comp

ACTUAL BEHAVIOR  
---------------
After creating new compensation plans and plan components copying and modifying
existing Plan components and performance  measures,
User is facing a peculiar situation. Output Expression formula is not returning the correct result, resulting in wrong earnings.


EXPECTED BEHAVIOR
-----------------------
Output Expression formula should return the correct result (ie earning)

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigator > Incentive Compensation > Compensation Plan
2. Create new Compensation plan > add Plan Components by doing a copy of existing ones
3. Complete setup and test expressions outputs  : earnings are not correct

See full test case

 1. Query Existing Comp Plan A.
 2. Click Duplicate Comp Plan button.
 3. Save
 4. Modify Comp Plan --> Add new Plan Component.
 5. Save
 6. Modify Target Incentive at Comp Plan level
 7. Modify Target Incentive Weight for Plan Components.
 8. Save
 9. Load Transactions file.
 10. Collect transactions.
 11. Classify transactions.
 12. Calculation.
 13. Earnings calculated as par previous Target Incentive(step 6) and Plan Components (step 7) instead of updated values.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot have a reliable calculation result

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms