Change Order Allowed For Zero Percent/Quantity PO Distribution Line (Doc ID 1662918.1)

Last updated on JANUARY 11, 2017

Applies to:

Oracle Fusion Purchasing - Version 11.1.11.1.0 and later
Oracle Fusion Purchasing Cloud Service - Version 11.1.11.1.0 and later
Information in this document applies to any platform.

Symptoms

The application is allowing for zero percent/quantity changes to be made at the Purchase Order (PO) Distribution Line level, which result in the PO Distribution Line having a value of zero.

Users expect that application should not allow for a zero precent/quantity PO distribution line.

Steps To Reproduce
1. Enter a Requisition with 1 line and split the Distribution between 2 charge accounts.
-- Submit the Requisition.
2. Create a PO for the Requisition.
3. Enter a Change Order.
-- Via the Distributions tab, change the quantity on any one of the lines to zero.
-- Submit the Change Order.
-- No zero percent/quantity error is displayed.
4. Approve the Change Order and observe that the resulting PO will have the one Distribution Line with zero quantity.

Cause

Sign In with your My Oracle Support account