How to change and save 'Cascade Option' in Project Template ( 'Edit Basic Information') ? (Doc ID 1966295.1)

Last updated on NOVEMBER 25, 2015

Applies to:

Oracle Fusion Project Foundation - Version 11.1.8.0.0 and later
Information in this document applies to any platform.

Goal

On : 11.1.8.0.0 version, Execute Project-Execute Project Tasks and Deliverables
 Not able to change 'Cascade Option' in Project Template
ACTUAL BEHAVIOR
-------------------
In the Project Template ( 'Edit Basic Information') 'Cascade Option' is not getting saved /changed to 'Cascade project finish date change to affected tasks' .

EXPECTED BEHAVIOR
----------------------------
In the Project Template ( 'Edit Basic Information') 'Cascade Option' is t getting saved to 'Cascade project finish date change to affected tasks' .

STEPS
-------
The issue can be reproduced at will with the following steps:

  Edit a Project Template that is already setup
  Navigate to 'Edit Basic Information' in selected template
  Change 'Cascade Option' drop down to 'Cascade project finish date change to affected tasks' from 'Do not cascade project date changes to tasks'
  Save and Close
  Go back to template setup and the 'Cascade Option' drop down is set back to 'Do not cascade project date changes to tasks'
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms