On : 11.1.8.0.0 version, Plan Project-Define Project Plan Tasks and Schedule

ACTUAL BEHAVIOR
---------------
In the Manage Project Plan page , "Go Up" and "Go to Top" buttons do not function properly

EXPECTED BEHAVIOR
-----------------------
 In the Manage Project Plan page , "Go Up" and "Go to Top" buttons function properly

Changes

 The issue can be reproduced at will with the following steps:
 1. Open a project with a number of tasks
2. Click on a low level task, that has at least two ancestors.
3. Click on the “Go Up” button
4. ISSUE1: The screen blinks; then returns with the task still selected. The “Go Up” and “Go to Top” and “Show as Top” icons are all grayed out. Must go to “List” view and back in order to clear.
5. Go to “List” view, then back to “Hierarchy” view
6. Click on a low level task, that has at least two ancestors.
7. Click on the “Go to Top” button
8. ISSUE2: The screen blinks; then returns with the task still selected. The “Go Up” and “Go to Top” and “Show as Top” icons are all grayed out. Must go to “List” view and back in order to clear.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms